During project execution, the team must adjust to significant procedural changes. What action should the project manager take to facilitate the team's adaptation?
Assign additional tasks to accommodate the changes.
Increase project oversight to ensure compliance.
Revise the project scope to include the procedural changes.
Arrange training sessions for the team on the procedural changes.
Providing training to team members ensures they understand and can effectively implement the new procedures introduced during the project. Training is essential in organizational change management to facilitate smooth transitions and adoption of new processes.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
Why is training important in adapting to procedural changes?
Open an interactive chat with Bash
What is organizational change management, and how does it relate to procedural changes?
Open an interactive chat with Bash
What other techniques, besides training, can help ensure a team's smooth adaptation to procedural changes?