CompTIA Project+ PK0-005 (V5) Practice Question

During an overnight maintenance window, a project manager must confirm that a newly installed database patch did not disrupt critical production services. Which of the following actions should the project manager perform to verify that the change was successful and the system remains fully operational?

  • Execute tests to ensure the system operates as expected.

  • Confirm that all users have been notified about the change.

  • Update the project schedule to reflect the change.

  • Review the change with senior management.

CompTIA Project+ PK0-005 (V5)
Basics of IT and Governance
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

SAVE $47
$390.00 $343.00
Bash, the Crucial Exams Chat Bot
AI Bot