CompTIA Project+ PK0-005 Practice Question
During a weekly meeting, your project sponsor requests an update on the project's progress. As the project manager, you need to prepare a project status report. Which of the following should you include to provide the most effective communication of the project's current status?
A summary of completed milestones and upcoming tasks.
Historical data from similar past projects.
Personal opinions on team members' performance.
An in-depth analysis of technical issues encountered.