During a project, team members are unsure about important deadlines and key dates. What should have been established during the planning phase to prevent this issue?

  • You selected this option

    Milestones in the project schedule

  • You selected this option

    A project charter

  • You selected this option

    A risk management plan

  • You selected this option

    A communication plan

CompTIA Project+ PK0-005
Project Life Cycle Phases
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot