CompTIA Project+ PK0-005 (V5) Practice Question

During a project, a vital system required for the next deliverable has failed. The support team is currently engaged in other tasks and cannot address the failure at this time. As the project manager, what is the BEST action to take?

  • Update the risk management plan to include potential system failures.

  • Have the project team focus on other tasks until the system is fixed.

  • Document the failure and wait for the support team to become available.

  • Escalate the issue to address the system failure as soon as possible.

CompTIA Project+ PK0-005 (V5)
Project Management Concepts
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

SAVE $47
$390.00 $343.00
Bash, the Crucial Exams Chat Bot
AI Bot