CompTIA Project+ PK0-005 Practice Question

At the beginning of a project, a project manager wants to establish how project documents and data will be stored, accessed, and secured throughout the project lifecycle. Which plan should the project manager develop during the initiation phase to address this?

  • You selected this option

    Establish a quality assurance plan

  • You selected this option

    Create a communication plan

  • You selected this option

    Prepare a procurement management plan

  • You selected this option

    Develop a records management plan

CompTIA Project+ PK0-005
Project Life Cycle Phases
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot