CompTIA Project+ PK0-005 Practice Question
At the beginning of a project, a project manager wants to establish how project documents and data will be stored, accessed, and secured throughout the project lifecycle. Which plan should the project manager develop during the initiation phase to address this?
Establish a quality assurance plan
Create a communication plan
Prepare a procurement management plan
Develop a records management plan