As a project manager, you are responsible for keeping external stakeholders informed about the progress of your project. Which method is the BEST for external status reporting?

  • Issue overall progress reports to external stakeholders as planned in the communication strategy.

  • Provide updates to external stakeholders whenever requested.

  • Share risk reports that detail internal issues with external stakeholders.

  • Conduct regular internal team meetings to monitor project progress.

CompTIA Project+ PK0-005 (V5)
Project Life Cycle Phases
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

SAVE $47
$390.00 $343.00
Bash, the Crucial Exams Chat Bot
AI Bot