As a project manager, you are responsible for keeping external stakeholders informed about the progress of your project. Which method is the BEST for external status reporting?
Share risk reports that detail internal issues with external stakeholders.
Conduct regular internal team meetings to monitor project progress.
Issue overall progress reports to external stakeholders as planned in the communication strategy.
Provide updates to external stakeholders whenever requested.