CompTIA Project+ PK0-005 Practice Question
As a project manager preparing for the launch of a new software application under tight deadlines and resource constraints, what should you prioritize?
Adding multiple features to outperform competitors.
Implementing core features essential for the product's primary function.
Developing a comprehensive application addressing various customer needs.
Extending the project timeline to include additional user-requested features.