As a project manager for an IT software development project, you have just received approval for a significant change request that will add new features to the project scope. What should you do next to ensure that the project reflects this change?
Direct the development team to immediately begin implementing the new features.
Consider delaying implementation of the change until further analysis is performed on its impact.
Update the project plan to incorporate the new features, adjusting timelines and resources as needed.
Schedule a meeting with stakeholders to review the approved changes and their implications.
The correct next step is to update the project plan to incorporate the new features, adjusting timelines, budgets, and resource allocations as necessary. This ensures that all aspects of the project are aligned with the new scope and provides clear guidance for the team moving forward. Directing the team to immediately begin implementation is incorrect because work should be based on the updated and approved project plan. Scheduling a meeting with stakeholders to review already approved changes would cause unnecessary delays, as the change has already been through the review and approval process. Considering delaying implementation for further analysis is also incorrect, as the impact analysis should have been completed prior to the change's approval.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is a project plan in project management?
Open an interactive chat with Bash
What is the significance of adjusting timelines and resources after a change request is approved?
Open an interactive chat with Bash
What is the change control process in project management?