CompTIA Project+ PK0-005 Practice Question

An IT project manager is overseeing the deployment of a new enterprise-level application. To facilitate future support and scalability, which type of documentation should the project manager ensure is meticulously created and maintained throughout the project?

  • You selected this option

    Training Materials

  • You selected this option

    Stakeholder Register

  • You selected this option

    Project Schedule

  • You selected this option

    Infrastructure Documentation

CompTIA Project+ PK0-005
Basics of IT and Governance
Your Score:
Settings & Objectives
N/A
N/A
N/A
N/A
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot