CompTIA Project+ PK0-005 Practice Question
A stakeholder requests a significant modification to the project scope during execution. The project manager evaluates the request and notes it will substantially affect the schedule and budget. Which project document should the project manager update to record this request and its disposition?
Issue log
Risk register
Defect log
Change log