CompTIA Project+ PK0-005 (V5) Practice Question

A software migration project has just completed sprint planning after a change request that shifted two critical milestones by two weeks. The change was reviewed, approved by the change control board (CCB), and the project schedule has been updated in the PMIS. Several stakeholders in different regions depend on the new dates for their resource allocations. According to the change control process, what should the project manager do next to make sure every stakeholder is aware of the updated timeline?

  • Rely on team members to review the updated timeline independently

  • Update the project documents and notify all stakeholders about the change

  • Record the change in project documentation with no further notification

  • Wait until the next team meeting to mention the change

CompTIA Project+ PK0-005 (V5)
Project Management Concepts
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

SAVE $47
$390.00 $343.00
Bash, the Crucial Exams Chat Bot
AI Bot