CompTIA Project+ PK0-005 Practice Question
A project team is in the planning phase of a complex project with many interdependent tasks. The project manager wants to use a tool to visualize task sequences, dependencies, and identify the longest path through the project. Which of the following tools should the project manager use?
Gantt chart
PERT chart
Milestone chart
Histogram