CompTIA Project+ PK0-005 Practice Question
A project manager receives a deliverable from a vendor but discovers it does not meet the project's specifications. What is the BEST action for the project manager to take in this situation?
Accept the deliverable to avoid project delays.
Proceed with the project and document the issue.
Modify the deliverable internally to meet specifications.
Request the vendor to address the discrepancies.