CompTIA Project+ PK0-005 Practice Question
A project manager on a software development project receives an email from a stakeholder requesting an additional feature be added to the project deliverables. What should the project manager do next?
Consider whether the request should be addressed formally.
Document the request in the change control log.
Discuss with the stakeholder the feasibility of changes at this stage.
Implement the change to satisfy the stakeholder.