CompTIA Project+ PK0-005 Practice Question
A project manager needs to track and manage issues reported by team members in real-time during the project execution phase. Which of the following tools would be MOST appropriate to use?
Issue log
Fishbone/Ishikawa diagram
Ticketing/case management system
Gantt chart