CompTIA Project+ PK0-005 Practice Question
A project manager needs to select a vendor for a new project. Before proceeding, they review industry publications, attend trade shows, and study competitor offerings to understand current market trends and potential suppliers. Which vendor evaluation technique is the project manager employing?
Request for Information (RFI)
Market research
Vendor site visits
Prequalified vendors