A project manager needs to select a vendor for a new project. Before proceeding, they review industry publications, attend trade shows, and study competitor offerings to understand current market trends and potential suppliers. Which vendor evaluation technique is the project manager employing?

  • You selected this option

    Request for Information (RFI)

  • You selected this option

    Market research

  • You selected this option

    Vendor site visits

  • You selected this option

    Prequalified vendors

CompTIA Project+ PK0-005
Project Management Concepts
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot