CompTIA Project+ PK0-005 Practice Question
A project manager needs to present a simplified overview of the project's key events to high-level stakeholders who are interested in major deliverables but not in the details. Which of the following tools should the project manager use to effectively communicate this information?
Gantt chart
Work breakdown structure
Project network diagram
Milestone chart