CompTIA Project+ PK0-005 Practice Question
A project manager needs to determine the sequence of activities and identify task dependencies to calculate the critical path of the project. Which of the following tools would BEST help achieve this goal?
Gantt chart
Budget burndown chart
Project network diagram
Milestone chart