CompTIA Project+ PK0-005 Practice Question
A project manager needs a visual tool to display task durations, start and end dates, and the dependencies between tasks on a horizontal time scale. Which of the following tools would BEST meet this need?
Gantt chart
Project network diagram
Milestone chart
PERT chart