CompTIA Project+ PK0-005 Practice Question

A project manager learns that a key supplier may not meet their delivery deadline, which could affect the project schedule and budget. Which tool should the project manager update to record this information and plan potential responses?

  • You selected this option

    Issue log

  • You selected this option

    Lessons learned register

  • You selected this option

    Change log

  • You selected this option

    Risk register

CompTIA Project+ PK0-005
Tools and Documentation
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot