CompTIA Project+ PK0-005 Practice Question
A project manager learns that a key supplier may not meet their delivery deadline, which could affect the project schedule and budget. Which tool should the project manager update to record this information and plan potential responses?
Issue log
Lessons learned register
Change log
Risk register