A project manager is working with an Agile team to plan the next development iteration. The team wants to ensure they have a clear focus and understand the primary objective for the upcoming work cycle. Which of the following should the team establish to BEST achieve this?
Define a clear goal for the iteration to guide the team's work.
Assign specific tasks to each team member ahead of the iteration.
Reprioritize the entire project backlog for the team.
Schedule daily meetings to coordinate activities during the iteration.
Defining a clear goal for the iteration provides the team with a shared objective, guiding their efforts during the work cycle. This is commonly referred to as a sprint goal in Scrum methodology. It helps the team focus on delivering specific value within the iteration. Assigning tasks to individuals or scheduling daily meetings are useful practices but do not establish the overarching objective for the iteration. Reprioritizing the entire project backlog is too broad and does not provide focus for the specific iteration.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is a sprint goal in Agile methodology?
Open an interactive chat with Bash
How is a sprint goal established during sprint planning?
Open an interactive chat with Bash
Why is establishing a sprint goal more effective than assigning tasks individually?