A project manager is scheduling tasks for a construction project. The foundation work (Task A) must finish before framing (Task B) can begin. Electrical wiring (Task C) can start any time after framing has started. Which of the following dependency types BEST describes the relationships among these tasks?
Finish-to-Start between Tasks A and B; Start-to-Start between Tasks B and C.
Finish-to-Finish between Tasks A and B; Start-to-Start between Tasks A and C.
Start-to-Finish between Tasks A and B; Finish-to-Start between Tasks B and C.
Finish-to-Start between Tasks A and B; Finish-to-Start between Tasks B and C.