CompTIA Project+ PK0-005 (V5) Practice Question

A project manager is prioritizing issues by evaluating which ones could most significantly affect the project's ability to deliver as planned. Which prioritization factor is she focusing on?

  • Issue severity

  • Impact to project

  • Scope of impact on stakeholders

  • Urgency