CompTIA Project+ PK0-005 Practice Question
A project manager is preparing the resource plan for an IT infrastructure project that involves installing new servers and networking hardware in a data center. Which of the following should be classified as a physical resource in the resource plan?
The network engineer assigned to configure the equipment
The project timeline outlining key deadlines
The rack units and power supplies for the servers
The budget allocated for purchasing the equipment