CompTIA Project+ PK0-005 Practice Question
A project manager is overseeing the rollout of a new company-wide software system designed to streamline operations. Which of the following actions would BEST facilitate user acceptance and effective use of the new system?
Migrate all historical data into the new software.
Offer thorough training sessions for all users.
Extensively tailor the software to match current processes.
Upgrade all equipment to the latest technology.