A project manager is overseeing the rollout of a new company-wide software system designed to streamline operations. Which of the following actions would BEST facilitate user acceptance and effective use of the new system?
Upgrade all equipment to the latest technology.
Migrate all historical data into the new software.
Extensively tailor the software to match current processes.
Offer thorough training sessions for all users.