CompTIA Project+ PK0-005 (V5) Practice Question

A project manager is overseeing the construction of a new data center. To align with the company's ESG goals, they must select an action that BEST minimizes the project's long-term environmental impact. Which of the following actions is the MOST effective?

  • Implement a comprehensive recycling program for waste generated during the construction phase.

  • Develop a green space with native plants on the property surrounding the facility.

  • Source all construction materials from local suppliers to reduce transportation emissions.

  • Design the facility to use renewable energy sources and energy-efficient cooling systems.

CompTIA Project+ PK0-005 (V5)
Basics of IT and Governance
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

SAVE $47
$390.00 $343.00
Bash, the Crucial Exams Chat Bot
AI Bot