CompTIA Project+ PK0-005 Practice Question

A project manager is overseeing a software development project and wants to adopt a methodology that enhances collaboration between developers and IT operations to automate and integrate their processes. Which of the following methodologies should the project manager choose?

  • You selected this option

    Waterfall

  • You selected this option

    DevOps

  • You selected this option

    PRINCE2

  • You selected this option

    Kanban

CompTIA Project+ PK0-005
Project Management Concepts
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot