CompTIA Project+ PK0-005 (V5) Practice Question

A project manager is leading a year-long software development project. Six months into the project, the client submits an approved change request for a significant expansion of the scope, which will add three months to the timeline. The original schedule is now unachievable. What is the BEST course of action for the project manager to ensure the schedule remains a useful performance measurement tool?

  • Continue tracking progress against the original, unachievable schedule.

  • Cancel the project due to the timeline changes.

  • Shorten the duration of remaining tasks to meet the original deadline.

  • Rebaseline the schedule to incorporate the approved changes.

CompTIA Project+ PK0-005 (V5)
Project Management Concepts
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

SAVE $47
$390.00 $343.00
Bash, the Crucial Exams Chat Bot
AI Bot