CompTIA Project+ PK0-005 (V5) Practice Question

A project manager is leading a team to develop a new mobile banking application. The project is under significant pressure due to a fixed launch date and a limited budget. The initial plan included over 50 features. To ensure a successful launch under these constraints, which of the following approaches should the project manager prioritize?

  • Requesting an extension to the project timeline to include all user-requested features.

  • Implementing only the core features essential for the application's primary function.

  • Adding several unique features to ensure the application outperforms competitors at launch.

  • Developing a comprehensive application addressing all 50+ originally planned features.

CompTIA Project+ PK0-005 (V5)
Project Life Cycle Phases
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

SAVE $47
$390.00 $343.00
Bash, the Crucial Exams Chat Bot
AI Bot