CompTIA Project+ PK0-005 (V5) Practice Question

A project manager is leading a network infrastructure upgrade. The vendor responsible for supplying and installing new server racks is consistently failing to meet the agreed-upon delivery dates outlined in the procurement contract. Which of the following is the BEST initial action for the project manager to take?

  • Immediately find a new vendor to take over the contract and mitigate further delays.

  • Instruct the project team to start working on tasks that do not depend on the server racks.

  • Review the vendor contract and schedule a meeting with the supplier to discuss the delays and a corrective action plan.

  • Update the project schedule and risk register to reflect the delays and inform stakeholders of the new timeline.

CompTIA Project+ PK0-005 (V5)
Project Life Cycle Phases
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

SAVE $47
$390.00 $343.00
Bash, the Crucial Exams Chat Bot
AI Bot