CompTIA Project+ PK0-005 (V5) Practice Question

A project manager is leading a distributed team across different countries. Some team members report difficulty accessing the team's primary communication platform due to local technical restrictions and limited bandwidth. Which action should the project manager take to address this communication challenge?

  • Evaluate and adopt communication tools that accommodate the technological constraints of all team members.

  • Schedule regular in-person meetings to compensate for the technological limitations.

  • Instruct team members to resolve their access issues with their local internet service providers.

  • Continue using the current communication platform and expect team members to adapt.

CompTIA Project+ PK0-005 (V5)
Project Management Concepts
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

SAVE $47
$390.00 $343.00
Bash, the Crucial Exams Chat Bot
AI Bot