A project manager is developing a records management plan for a new project. Which of the following elements is most critical to include to ensure proper handling of project information?

  • A list of key stakeholders and their roles.

  • Guidelines for storing, accessing, and disposing of project data.

  • The project budget allocation and expenditure tracking methods.

  • A schedule of project meetings and communication plan.

CompTIA Project+ PK0-005 (V5)
Project Life Cycle Phases
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

SAVE $47
$390.00 $343.00
Bash, the Crucial Exams Chat Bot
AI Bot