CompTIA Project+ PK0-005 (V5) Practice Question

A project manager is dealing with an issue that the project team cannot resolve on their own. According to best practices in issue management, what is the BEST next step the project manager should take to address the issue?

  • Postpone addressing the issue until the next project review meeting.

  • Document the issue and proceed with the project plan as scheduled.

  • Escalate the issue to the appropriate higher authority according to the escalation plan.

  • Assign additional resources to the team to help resolve the issue.

CompTIA Project+ PK0-005 (V5)
Project Management Concepts
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

SAVE $47
$390.00 $343.00
Bash, the Crucial Exams Chat Bot
AI Bot