🔥 40% Off Crucial Exams Memberships — This Week Only

3 days, 14 hours remaining!

CompTIA Project+ PK0-005 (V5) Practice Question

A project manager has received approval for a change request, updated the project plan to reflect the new tasks, budget, and schedule adjustments, and distributed the revised plan to the team. According to the formal change control process defined for the project, which subsequent step involves the project team actually carrying out the work described in the revised plan?

  • Implement changes

  • Conduct impact assessments

  • Validate the change implementation

  • Document change recommendations

CompTIA Project+ PK0-005 (V5)
Project Management Concepts
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

SAVE $47
$390.00 $343.00
Bash, the Crucial Exams Chat Bot
AI Bot