A project manager has just overseen the successful implementation and validation of an approved change. According to the change control process, what is the next critical step to ensure all stakeholders are aware of the update?
Close the change request in the change control log.
Communicate the change deployment to stakeholders.
Update the project plan to reflect the change.
Escalate the change status to the Change Control Board (CCB).
After a change is implemented and validated, the next critical step in the process is to communicate the deployment to all relevant stakeholders. This ensures everyone is aware that the change is complete and live, preventing confusion and ensuring alignment. Updating the project plan occurs before implementation, and closing the change request is one of the final administrative actions after communication is complete.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
Why is stakeholder communication important after implementing a change?
Open an interactive chat with Bash
What methods can be used to communicate changes to stakeholders?
Open an interactive chat with Bash
What information should be included when communicating a change to stakeholders?