CompTIA Project+ PK0-005 (V5) Practice Question

A project manager has just finished defining the work breakdown structure (WBS) and is now preparing to develop the project schedule. Which of the following activities is the MOST critical prerequisite for creating a realistic and resource-constrained schedule?

  • Developing a transition plan

  • Performing an initial risk assessment

  • Assigning project resources

  • Developing the quality assurance (QA) plan

CompTIA Project+ PK0-005 (V5)
Project Life Cycle Phases
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

SAVE $47
$390.00 $343.00
Bash, the Crucial Exams Chat Bot
AI Bot