CompTIA Project+ PK0-005 (V5) Practice Question

A project manager discovers that a critical software used in an ongoing project will soon be discontinued by the vendor. To ensure the project continues without disruption, what is the BEST action the project manager should take?

  • Prepare the team to function without relying on the software

  • Use the software until it becomes non-operational and then address the issues

  • Rely on the vendor to provide a replacement

  • Develop a plan for replacing the software before it is discontinued

CompTIA Project+ PK0-005 (V5)
Project Management Concepts
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

SAVE $47
$390.00 $343.00
Bash, the Crucial Exams Chat Bot
AI Bot