A project manager calculates the total resource needs over the duration of the project without changing task start or end dates. This approach is an example of resource leveling.
True
False
A project manager calculates the total resource needs over the duration of the project without changing task start or end dates. This approach is an example of resource leveling.
True
False
This statement is False. The process described is resource loading, not resource leveling. Resource loading involves assigning resources to tasks and calculating the amount of resources required over time without altering the project schedule. Resource leveling, on the other hand, involves adjusting the project schedule to resolve resource over-allocation by delaying tasks or extending timelines.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All IT & Cybersecurity Package plans include the following perks and exams .
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
Access our store with even bigger discounts than before.
Unlimited access to all performance questions and be prepared for the real thing.
All IT & Cybersecurity Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.