CompTIA Project+ PK0-005 Practice Question
A company is implementing a new system to manage customer relationships, which will store sensitive customer data. As the project manager, which consideration is most important to ensure compliance during this project?
Select a cloud provider with advanced security features for the new system
Ensure the new system integrates seamlessly with existing software
Verify that the project adheres to applicable data privacy laws and regulations
Provide training to the team on the new system's functionalities