Your organization has just completed a three-year digital-transformation program that replaced legacy systems and launched a customer self-service portal across four business units. The steering committee has asked you, as program manager, to prepare the final close-out plan for next month's gate review.

Stakeholders are pulling in different directions:

  • The CFO wants an immediate financial reconciliation to release unused funds.
  • Procurement is anxious to terminate outstanding vendor contracts to avoid additional liabilities.
  • Functional managers are pressuring HR to release program staff so they can be reassigned to new initiatives.
    Several executives, however, are worried that the hard-won insights and undocumented work-arounds developed during the transformation will be lost once resources are dispersed. To mitigate that risk and satisfy governance requirements for knowledge retention, which activity should you emphasize first in the close-out plan?
  • Release program personnel to their functional managers in accordance with the workforce reallocation policy

  • Issue stop-work notices and formally close all remaining supplier contracts

  • Complete cost-variance analysis and submit the financial closure package to the finance director

  • Facilitate lessons-learned workshops, compile findings, and archive program documentation in the enterprise knowledge repository

PgMP
Governance
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot