PgMP Practice Question

Your organization has approved a three-year digital modernization initiative comprising multiple related projects. Before assigning component project managers, the newly appointed program manager must produce a single document that formally authorizes the program, links it to the approved business case, and summarizes strategic objectives, high-level scope, benefits, assumptions, constraints, and stakeholder commitments. What document is required?

  • Program charter

  • Program roadmap

  • Benefits management plan

  • Stakeholder engagement plan

PgMP
Program Life Cycle Management
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot