PgMP Practice Question

Your five-year organizational transformation program is entering the closure phase. All component projects are finished, and you must obtain governance approval for formal financial closeout next week. To demonstrate that every vendor payment, internal charge, and budget transfer is settled and traceable, which action should you prioritize before submitting the closure package to the steering committee?

  • Reconcile the final program ledger to produce a detailed statement of accounts and variance explanations, confirming all expenditures and obligations are closed.

  • Secure executive sign-off on the program's benefits sustainment plan and funding commitments.

  • Archive all program financial records in the organization's repository for future audits.

  • Obtain legal confirmation that all procurement contracts have been formally closed out.

PgMP
Program Life Cycle Management
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot