You are managing a software development program and have just completed interviews with key stakeholders. One of the sponsors has identified a potential risk related to emerging data privacy regulations that could affect the program's timeline and budget. What should you do next to appropriately address this risk in your program risk management plan?
Document the risk in the program's risk register but take no immediate action.
Ignore the risk since it was not identified during the initial planning phase.
Acknowledge the risk but decide to monitor it without adding it to the risk register
Include it in the program risk register, evaluate the potential impact and likelihood of the data privacy regulation risk, then with appropriate mitigation strategies.
The correct answer involves assessing the identified risk's impact and likelihood, then incorporating it into the risk management plan with mitigation strategies. This ensures the program proactively addresses potential threats. The other options either ignore the risk, delay action, or document without proper analysis, which are inadequate responses.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What are data privacy regulations?
Open an interactive chat with Bash
What is a risk management plan?
Open an interactive chat with Bash
What are mitigation strategies in risk management?
Open an interactive chat with Bash
PgMP
Stakeholder Engagement
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Project Management Package Join Premium for Full Access