PgMP Practice Question

Which of the following is a primary activity when chartering and initiating constituent projects within a program?

  • Conducting a SWOT analysis for each project

  • Developing a detailed program scope statement

  • Performing statistical analysis on program performance

  • Assigning project managers and allocating appropriate resources

PgMP
Program Life Cycle Management