PgMP Practice Question
Which approach best supports the development of a schedule that captures interconnected phases and resources for a large initiative with multiple workstreams?
None of these
Build a consolidated plan that aligns milestones, dependencies, and shared resources from each area
Maintain separate schedules for each workstream without combining them
Focus on cost-based tracking to measure overall progress for major tasks