Defining clear measures in the governance model for moving an issue from lower management to higher authorities ensures consistent oversight. Approaches that rely on one individual or require each team member to handle issues until they are critical can lead to delays or mismatched accountability. The issues and concerns exceeding thresholds are discussed in scheduled program reviews (phase gates, health checks etc), however without knowing those checkpoints (thresholds), the concern cannot be discussed in the program reviews
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What are triggers and thresholds in program governance?
Open an interactive chat with Bash
Why is it important to define escalation mechanisms in a governance model?
Open an interactive chat with Bash
How do program reviews differ from defined escalation triggers and thresholds?
Open an interactive chat with Bash
PgMP
Governance
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Pass with Confidence.
Project Management Package
You have hit the limits of our free tier, become a Premium Member today for unlimited access.
Military, Healthcare worker, Gov. employee or Teacher? See if you qualify for a Community Discount.
Monthly
$9.99
$9.99/mo
Billed monthly, Cancel any time.
3 Month Pass
$19.99
$6.66/mo
One time purchase of $19.99, Does not auto-renew.
BEST DEAL
Lifetime Pass
$29.99
One time purchase, Good for life.
What You Get
All Project Management Package plans include the following perks and exams .