Which action most supports synergy and efficiency gains while keeping relevant groups informed?
Combine overlapping work streams when identified and reflect changes in progress updates to leaders.
Postpone synergy discussions until key component projects are underway.
Use cost-benefit ratios for each component and evaluate opportunities across them.
Limit feedback to sponsor input and consider perspectives from other stakeholders.